Church Fire Updates and Gallery
For I know the plans that I have for you,’ declares the Lord, ‘plans for welfare and not for calamity to give you a future and a hope ~ Jeremiah 29:11 (NASB)
Thank you all for the continued prayers and support! We are very excited to see what God has in-store for our new building.
Update: 02/15/20
The plans for the new church have been approved by the county. The church board is in the process of selecting and reviewing contractor bids.
Update: 08/12/19
The church building plans are being reviewed by the engineers. Bids have come back for the electrical, plumbing, sprinklers, and other constriction duties. The General Contractor will be announced soon.
Update: 05/15/19
The draft was sent in for code review and several changes needed to be made. After reviewing another updated layout draft, the plans were accepted by the code reviewer. Bids will now be sent out for electrical, plumbing, sprinklers, and other construction building duties.
Update: 04/13/19
The architect has drafted up the new building plans, including the interior and exterior layout. The deacons will be approving the draft, and the architect will send them out for final code approval.
Update: 01/13/19
The new church building layout has been approved by the deacon board and church members. The plans are now waiting on bid from the architects. The old church grounds are being prepped for the new building.
Update: 12/09/18
The new church building has passed the "Land Use" from the county. The suggested layouts by the members have been handed off to a general contractor. Building is expected to commence in February if all continues to move forward as planned.
Update: 10/12/18
The old building is cleared. The new building committee will be selecting the top layouts people submitted and will present the best options to the church board members.
Update: 09/21/2018
Temporary winter building is complete and church services will be held in this building until further notice. A committee was established to review the new church building layout. Demolition of old building is underway.
Update: 08/026/2018
Temporary winter building is now under construction, 08/27 - 08/3. Building layout is still underway and a committee to review the drafts has been formed. Insurance meetings and bids are still in process.
Update: 08/01/2018
Building for winter season use found and secured. Location is next to Hillside Bible Church. Photos and address coming soon.
Update: 07/18/2018
Insurance claim to be finalized soon and construction quotes are still coming in. A few of the church members visited a possible building to use during this coming winter season, details coming soon.
Update: 06/22/2018
A large tent and speaker system was donated for church use. Church board & insurance meetings still underway.
Update: 06/12/2018
The church bell was rescued and is in a safe place.
Update: 06/11/2018
1. Cause of fire per the Forest Grove Fire & Rescue: Electrical Failure
2. Insurance Inspector to verify and review information this week
Update: 06/09/2018
Dear Church Family,
As many of you may already know, our building has nearly burnt down today, 06/09/2018. We are truly blessed that no one was injured or in the building at the time. Even though our building has gone, our church family is still alive and well and are very excited to see what God has in store for us. Oh, give thanks to the Lord, for He is Good! For His mercy endures forever. ~ Psalms 136:1
Thank you to all of the firefighters and support teams that worked hard to put out the fire. We also thank everyone for their prayers and support.
Several of the church members will be there in the morning (06/10/2018 @9:45 am) for prayer and fellowship, you are more than welcome to join. Note: Since there is no building, we will be meeting on the church grounds. Don't forget to bring your umbrella if you decide to come out.
Updates will be posted here. Let the rebuilding begin!
Article By Gales Creek Journal:
https://galescreekjournal.com/news/hillside-bible-church-destroyed-in-fire-one-firefighter-injured/-
The plans for the new church have been approved by the county. The church board is in the process of selecting and reviewing contractor bids.
Update: 08/12/19
The church building plans are being reviewed by the engineers. Bids have come back for the electrical, plumbing, sprinklers, and other constriction duties. The General Contractor will be announced soon.
Update: 05/15/19
The draft was sent in for code review and several changes needed to be made. After reviewing another updated layout draft, the plans were accepted by the code reviewer. Bids will now be sent out for electrical, plumbing, sprinklers, and other construction building duties.
Update: 04/13/19
The architect has drafted up the new building plans, including the interior and exterior layout. The deacons will be approving the draft, and the architect will send them out for final code approval.
Update: 01/13/19
The new church building layout has been approved by the deacon board and church members. The plans are now waiting on bid from the architects. The old church grounds are being prepped for the new building.
Update: 12/09/18
The new church building has passed the "Land Use" from the county. The suggested layouts by the members have been handed off to a general contractor. Building is expected to commence in February if all continues to move forward as planned.
Update: 10/12/18
The old building is cleared. The new building committee will be selecting the top layouts people submitted and will present the best options to the church board members.
Update: 09/21/2018
Temporary winter building is complete and church services will be held in this building until further notice. A committee was established to review the new church building layout. Demolition of old building is underway.
Update: 08/026/2018
Temporary winter building is now under construction, 08/27 - 08/3. Building layout is still underway and a committee to review the drafts has been formed. Insurance meetings and bids are still in process.
Update: 08/01/2018
Building for winter season use found and secured. Location is next to Hillside Bible Church. Photos and address coming soon.
Update: 07/18/2018
Insurance claim to be finalized soon and construction quotes are still coming in. A few of the church members visited a possible building to use during this coming winter season, details coming soon.
Update: 06/22/2018
A large tent and speaker system was donated for church use. Church board & insurance meetings still underway.
Update: 06/12/2018
The church bell was rescued and is in a safe place.
Update: 06/11/2018
1. Cause of fire per the Forest Grove Fire & Rescue: Electrical Failure
2. Insurance Inspector to verify and review information this week
Update: 06/09/2018
Dear Church Family,
As many of you may already know, our building has nearly burnt down today, 06/09/2018. We are truly blessed that no one was injured or in the building at the time. Even though our building has gone, our church family is still alive and well and are very excited to see what God has in store for us. Oh, give thanks to the Lord, for He is Good! For His mercy endures forever. ~ Psalms 136:1
Thank you to all of the firefighters and support teams that worked hard to put out the fire. We also thank everyone for their prayers and support.
Several of the church members will be there in the morning (06/10/2018 @9:45 am) for prayer and fellowship, you are more than welcome to join. Note: Since there is no building, we will be meeting on the church grounds. Don't forget to bring your umbrella if you decide to come out.
Updates will be posted here. Let the rebuilding begin!
Article By Gales Creek Journal:
https://galescreekjournal.com/news/hillside-bible-church-destroyed-in-fire-one-firefighter-injured/-
Some News Coverage